Project description
The conservative restoration and enhancement project includes a series of interventions aimed at preserving, restoring and enhancing the fountain. Below are the main activities planned:
- biocidal treatment: a biocidal treatment will be performed to eliminate any unwanted biological organisms, such as algae, moss or mould that may cause damage to the fountain. The treatment will preserve the surfaces and prevent the growth of harmful organisms;
- cleaning operations: cleaning operations will be conducted across all surfaces of the fountain, including any limestone deposits. The intervention may require the use of specific techniques and products to remove dirt, deposits and limestone residues;
- plastering and colour scheme overhaul: the plasters on the fountain will be overhauled, repaired and replaced. An additional colour scheme overhaul will be performed to restore the original aesthetic appearance of the fountain;
- overhaul and restoration of metal elements functionality: metal elements, such as brackets, pins or other decorative details, will undergo a complete overhaul to assess their functionality and state of preservation. If required, repairs or replacements will be carried out to ensure their efficient operation;
- aesthetic overhaul: the fountain will undergo an aesthetic overhaul to assess its overall appearance and identify any damaged, missing parts or that need specific intervention to improve its aesthetics;
- application of the final protective coating: a final protective coating will be applied to the fountain’s surfaces to preserve them from deterioration caused by weather and wear;
- waterproofing restoration of basins: the waterproofing of the fountain basins will be restored to ensure water tightness in the basins;
- overhaul of the end section of the water system: the final section of the water system will be inspected to verify its functionality and proceed to repair or replacement where required.
Status
Planning
Tender stage
Site
End of Work
Funding source
PNRR
Amount allocated
356.000,00 €