Bridge Maintenance Plan

Implementing party

Roma Capitale

Project description

The plan includes maintenance work on joints, supports, water collection systems, cleaning up weeds, replacing guardrail barriers, and upgrading the pavement. The areas covered by the intervention will be:

  • Ponte Marconi; 
  • Viaduct at Via Palmiro Togliatti overpassing Via Collatina Vecchia and the FS line;
  • Ramp connecting A24 and East Orbital Road (Tangenziale Est); 
  • Via Nomentana flyover at Caserma Aimone Bianchi height overpassing the East Orbital Road;
  • Elevated causeway from the Prenestina interchange;
  • Ponte della Scafa;
  • Via Alessandro Ruspoli/Dragoncello pedestrian bridge;
  • Cristoforo Colombo Viaduct;
  • Via Mario Pastore Highway A1 Flyover;
  • Via Flaminia Bridge;
  • Flyover of Via Leone XIII overpassing Via Aurelia antica (Villa Doria Pamphili);
  • Bridge in Via Portuense over the Fosso della Magliana;
  • Cristoforo Colombo flyover overpassing Via Dell’Atletica and Viale Del Pattinaggio;
  • Cristoforo Colombo Viaduct over EUR Pond;
  • Elio Chianesi overpass GRA flyover;
  • Foro Italico flyover (Ponte Morandi) on Corso Francia;
  • Tangenziale Est (East Orbital Road), sections from Viale Castrense and Via Prenestina;
  • Viaduct of Via Tuscolana;
  • Viale Duilio Cambellotti;
  • Tor Bella Monaca viaduct on Via Aspertini;
  • Ponte di Salone over the Aniene River;
  • Via Del Fuoco Sacro Flyover on Via Tor Bella Monaca;
  • Zelia Nuttal Viaduct;
  • Eur Pond Viaduct;
  • Bridge of Via della Stazione di Cesano;
  • Gronchi Viaduct;
  • Via Vigne Nuove Viaduct;
  • Del Cavaliere Viaduct;
  • Foro Italico Viaduct (Ponte Morandi); 
  • Ponte Sant'Angelo;
  • Ponte Milvio.

At present, about 12 km of infrastructure including bridges and viaducts have already been upgraded. 

 

Status

Planning
Tender stage
Site
End of Work

Estimated completion date

Second Quarter 2026

Funding source

Roma Capitale Budget

Amount allocated

2.600.000,00 €